Problems On Time and Work :
1) A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
|
| ||||||
|
|
Solution :
A's 1 day's work = | 1 | ; |
15 |
B's 1 day's work = | 1 | ; |
20 |
(A + B)'s 1 day's work = | 1 | + | 1 | = | 7 | . | ||
15 | 20 | 60 |
(A + B)'s 4 day's work = | 7 | x 4 | = | 7 | . | ||
60 | 15 |
Therefore, Remaining work =1-7/15=8/15 | . | ||||||||||||||||||||||||||
2) A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
|
Solution :
(A + B + C)'s 1 day's work = | 1 | , |
4 |
A's 1 day's work = | 1 | , |
16 |
B's 1 day's work = | 1 | . |
12 |
C's 1 day's work = | 1 | - | 1 | + | 1 | = | 1 | - | 7 | = | 5 | . | ||||
4 | 16 | 12 | 4 | 48 | 48 |
So, C alone can do the work in | 48 | = 9 | 3 | days. |
5 | 5 |
3) A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days | 15 days | ||
16 days | 18 days |
Solution :
A's 2 day's work = | 1 | x 2 | = | 1 | . | ||
20 | 10 |
(A + B + C)'s 1 day's work = | 1 | + | 1 | + | 1 | = | 6 | = | 1 | . | ||
20 | 30 | 60 | 60 | 10 |
Work done in 3 days = | 1 | + | 1 | = | 1 | . | ||
10 | 10 | 5 |
Now, | 1 | work is done in 3 days. |
5 |
Whole work will be done in (3 x 5) = 15 days.
4) A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days |
| ||||||
25 days | 30 days |
Solution :
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes | 3 | x 60 | = 90 days. | ||
2 |
So, A takes 30 days to do the work.
A's 1 day's work = | 1 |
30 |
B's 1 day's work = | 1 |
90 |
(A + B)'s 1 day's work = | 1 | + | 1 | = | 4 | = | 2 | ||
30 | 90 | 90 | 45 |
A and B together can do the work in | 45 | = 22 | 1 | days. |
2 | 2 |
Rs. 375 | Rs. 400 | ||
Rs. 600 | Rs. 800 |
Solution :
C's 1 day's work = | 1 | - | 1 | + | 1 | = | 1 | - | 7 | = | 1 | . | ||
3 | 6 | 8 | 3 | 24 | 24 |
A's wages : B's wages : C's wages = | 1 | : | 1 | : | 1 | = 4 : 3 : 1. |
6 | 8 | 24 |
C's share (for 3 days) = Rs. | 3 x | 1 | x 3200 | = Rs. 400. | ||
24 |
4 days | 5 days | ||
6 days | 7 days |
Solution : Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.
Then, 6x + 8y = | 1 | and 26x + 48y = | 1 | . |
10 | 2 |
Solving these two equations, we get : x = | 1 | and y = | 1 | . |
100 | 200 |
(15 men + 20 boy)'s 1 day's work = | 15 | + | 20 | = | 1 | . | ||
100 | 200 | 4 |
15 men and 20 boys can do the work in 4 days.
7) A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?8 hours | 10 hours | ||
12 hours | 24 hours |
Solution :
A's 1 hour's work = | 1 | ; |
4 |
(B + C)'s 1 hour's work = | 1 | ; |
3 |
(A + C)'s 1 hour's work = | 1 | . |
2 |
(A + B + C)'s 1 hour's work = | 1 | + | 1 | = | 7 | . | ||
4 | 3 | 12 |
B's 1 hour's work = | 7 | - | 1 | = | 1 | . | ||
12 | 2 | 12 |
B alone will take 12 hours to do the work.
8) A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
15 days | 20 days | ||
25 days | 30 days |
Solution :
Whole work is done by A in | 20 x | 5 | = 25 days. | ||
4 |
Now, | 1 - | 4 | i.e., | 1 | work is done by A and B in 3 days. | ||
5 | 5 |
Whole work will be done by A and B in (3 x 5) = 15 days.
A's 1 day's work = | 1 | , (A + B)'s 1 day's work = | 1 | . |
25 | 15 |
B's 1 day's work = | 1 | - | 1 | = | 4 | = | 2 | . | ||
15 | 25 | 150 | 75 |
So, B alone would do the work in | 75 | = 37 | 1 | days. | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
2 | 2 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
9) A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
Solution :
A's 1 day's work = (B + C)'s 1 day's work .... (ii)
So, B alone could do the work in 25 days. 10) A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
Solution :
So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M. 11) P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
|
Q can complete the work in (8 x 10) hrs. = 80 hrs.
P's1 hour's work = | 1 | and Q's 1 hour's work = | 1 | . |
96 | 80 |
(P + Q)'s 1 hour's work = | 1 | + | 1 | = | 11 | . | ||
96 | 80 | 480 |
So, both P and Q will finish the work in | 480 | hrs. | ||
11 |
Number of days of 8 hours each = | 480 | x | 1 | = | 60 | days = 5 | 5 | days. | ||
11 | 8 | 11 | 11 |
3 | 5 | ||
7 | Cannot be determined |
Solution :
1 woman's 1 day's work = | 1 |
70 |
1 child's 1 day's work = | 1 |
140 |
(5 women + 10 children)'s day's work = | 5 | + | 10 | = | 1 | + | 1 | = | 1 | ||||
70 | 140 | 14 | 14 | 7 |
5 women and 10 children will complete the work in 7 days.
13) A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?5 |
| |||||
6 | 8 |
Solution :
B's 10 day's work = | 1 | x 10 | = | 2 | . | ||
15 | 3 |
Remaining work = | 1 - | 2 | = | 1 | . | ||
3 | 3 |
Now, | 1 | work is done by A in 1 day. |
18 |
1 | work is done by A in | 18 x | 1 | = 6 days. | |||
3 | 3 |
14) A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
4 days | 6 days | ||
8 days | 12 days |
Solution :
Suppose A, B and C take x, | x | and | x | days respectively to finish the work. |
2 | 3 |
Then, | 1 | + | 2 | + | 3 | = | 1 | ||
x | x | x | 2 |
6 | = | 1 | |
x | 2 |
x = 12.
So, B takes (12/2) = 6 days to finish the work.
15) Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?3 : 4 | 4 : 3 | ||
5 : 3 | Data inadequate |
1 woman's 1 day's work = | 1 | . |
320 |
(16 x 15) men can complete the work in 1 day.
1 man's 1 day's work = | 1 |
240 |
So, required ratio |
| ||||||
| |||||||
= 4 : 3 (cross multiplied) |
No comments:
Post a Comment