Monday, April 2, 2012

Problems On Time and Work


Problems On Time and Work :
1) A can do a work in 15 days and B in 20 days. If they work on it together for 4 days, then the fraction of the work that is left is :
1
4
1
10
7
15
8
15
Solution :
A's 1 day's work =
1
;
15

B's 1 day's work =
1
;
20

(A + B)'s 1 day's work =
1
+
1
=
7
.
15
20
60

(A + B)'s 4 day's work =
7
x 4
=
7
.
60
15

Therefore, Remaining work =1-7/15=8/15





.








2) A can lay railway track between two given stations in 16 days and B can do the same job in 12 days. With help of C, they did the job in 4 days only. Then, C alone can do the job in:
9
1
days
5
9
2
days
5
9
3
days
5
10








Solution :
(A + B + C)'s 1 day's work =
1
,
4

A's 1 day's work =
1
,
16

B's 1 day's work =
1
.
12

C's 1 day's work =
1
-
1
+
1
=
1
-
7
=
5
.
4
16
12
4
48
48

So, C alone can do the work in
48
= 9
3
days.
5
5
3) A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?
12 days
15 days
16 days
18 days

Solution :
A's 2 day's work =
1
x 2
=
1
.
20
10

(A + B + C)'s 1 day's work =
1
+
1
+
1
=
6
=
1
.
20
30
60
60
10

Work done in 3 days =
1
+
1
=
1
.
10
10
5

Now,
1
work is done in 3 days.
5
Whole work will be done in (3 x 5) = 15 days.
4) A is thrice as good as workman as B and therefore is able to finish a job in 60 days less than B. Working together, they can do it in:
20 days
22
1
days
2
25 days
30 days

Solution :
Ratio of times taken by A and B = 1 : 3.
The time difference is (3 - 1) 2 days while B take 3 days and A takes 1 day.
If difference of time is 2 days, B takes 3 days.
If difference of time is 60 days, B takes
3
x 60
= 90 days.
2
So, A takes 30 days to do the work.
A's 1 day's work =
1
30

B's 1 day's work =
1
90

(A + B)'s 1 day's work =
1
+
1
=
4
=
2
30
90
90
45

A and B together can do the work in
45
= 22
1
days.
2
2
5) A alone can do a piece of work in 6 days and B alone in 8 days. A and B undertook to do it for Rs. 3200. With the help of C, they completed the work in 3 days. How much is to be paid to C?
Rs. 375
Rs. 400
Rs. 600
Rs. 800

Solution :
C's 1 day's work =
1
-
1
+
1
=
1
-
7
=
1
.
3
6
8
3
24
24

A's wages : B's wages : C's wages =
1
:
1
:
1
= 4 : 3 : 1.
6
8
24

C's share (for 3 days) = Rs.
3 x
1
x 3200
= Rs. 400.
24
6) If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
4 days
5 days
6 days
7 days

Solution : Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.
Then, 6x + 8y =
1
and 26x + 48y =
1
.
10
2

Solving these two equations, we get : x =
1
and y =
1
.
100
200

(15 men + 20 boy)'s 1 day's work =
15
+
20
=
1
.
100
200
4
*  15 men and 20 boys can do the work in 4 days.
7) A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
8 hours
10 hours
12 hours
24 hours
Solution :
A's 1 hour's work =
1
;
4

(B + C)'s 1 hour's work =
1
;
3

(A + C)'s 1 hour's work =
1
.
2

(A + B + C)'s 1 hour's work =
1
+
1
=
7
.
4
3
12

B's 1 hour's work =
7
-
1
=
1
.
12
2
12
B alone will take 12 hours to do the work.
8) A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
15 days
20 days
25 days
30 days
Solution :
Whole work is done by A in
20 x
5
= 25 days.
4

Now,
1 -
4
i.e.,
1
work is done by A and B in 3 days.
5
5
Whole work will be done by A and B in (3 x 5) = 15 days.
A's 1 day's work =
1
, (A + B)'s 1 day's work =
1
.
25
15

B's 1 day's work =
1
-
1
=
4
=
2
.
15
25
150
75

So, B alone would do the work in
75
= 37
1
days.
2
2





9) A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in:
15 days
20 days
25 days
30 days
Solution :
(A + B)'s 1 day's work =
1
10

C's 1 day's work =
1
50

(A + B + C)'s 1 day's work =
1
+
1
=
6
=
3
. .... (i)
10
50
50
25
A's 1 day's work = (B + C)'s 1 day's work .... (ii)
From (i) and (ii), we get: 2 x (A's 1 day's work) =
3
25

A's 1 day's work =
3
.
50

B's 1 day's work
1
-
3
=
2
=
1
.
10
50
50
25
So, B alone could do the work in 25 days.
10) A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
11:30 A.M.
12 noon
12:30 P.M.
1:00 P.M.

Solution :

(P + Q + R)'s 1 hour's work =
1
+
1
+
1
=
37
.
8
10
12
120

Work done by P, Q and R in 2 hours =
37
x 2
=
37
.
120
60

Remaining work =
1 -
37
=
23
.
60
60

(Q + R)'s 1 hour's work =
1
+
1
=
11
.
10
12
60

Now,
11
work is done by Q and R in 1 hour.
60

So,
23
work will be done by Q and R in
60
x
23
=
23
hours 2 hours.
60
11
60
11
So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.
11) P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work?
5
5
11
5
6
11
6
5
11
6
6
11




Solution : P can complete the work in (12 x 8) hrs. = 96 hrs.
Q can complete the work in (8 x 10) hrs. = 80 hrs.
P's1 hour's work =
1
and Q's 1 hour's work =
1
.
96
80

(P + Q)'s 1 hour's work =
1
+
1
=
11
.
96
80
480

So, both P and Q will finish the work in
480
hrs.
11

Number of days of 8 hours each =
480
x
1
=
60
days = 5
5
days.
11
8
11
11
12) 10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
3
5
7
Cannot be determined
Solution :
1 woman's 1 day's work =
1
70

1 child's 1 day's work =
1
140

(5 women + 10 children)'s day's work =
5
+
10
=
1
+
1
=
1
70
140
14
14
7
5 women and 10 children will complete the work in 7 days.
13) A can finish a work in 18 days and B can do the same work in 15 days. B worked for 10 days and left the job. In how many days, A alone can finish the remaining work?
5
5
1
2
6
8
Solution :
B's 10 day's work =
1
x 10
=
2
.
15
3

Remaining work =
1 -
2
=
1
.
3
3

Now,
1
work is done by A in 1 day.
18

1
work is done by A in
18 x
1
= 6 days.
3
3
14)   A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
4 days
6 days
8 days
12 days
Solution :
Suppose A, B and C take x,
x
and
x
days respectively to finish the work.
2
3

Then,
1
+
2
+
3
=
1
x
x
x
2

6
=
1
x
2
x = 12.
So, B takes (12/2) = 6 days to finish the work.
15) Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman?
3 : 4
4 : 3
5 : 3
Data inadequate
Solution : (20 x 16) women can complete the work in 1 day.
1 woman's 1 day's work =
1
.
320
(16 x 15) men can complete the work in 1 day.
1 man's 1 day's work =
1
240

So, required ratio
=
1
:
1
240
320

=
1
:
1
3
4

= 4 : 3 (cross multiplied)

No comments:

Post a Comment